Former Acme Visible Records Site
Currently Owned by Wilson Jones Company
5327 Three Notch’d Road Crozet, Virginia 22932
April 2, 2018
Update: 02
Dear Neighbor,
As a follow-up to our October update letter, enclosed is the revised schedule for the current Interim Measures (IM) soil remediation and ongoing RCRA tasks at the Former Acme Visible Records site (Click here for PDF). We anticipate completing the soil remediation measures around June or July 2018, depending on weather and field conditions. We will keep you apprised of upcoming tasks and any schedule changes.
For your convenience, below is a summary of the anticipated upcoming remediation activities taking place during the month of April, 2018:
Week of April 01, 2018
– Equipment Mobilization and Additional Concrete Cutting, and initiate Soil Excavation, Hauling, and Disposal on the North Side of the WJC Site. *Please note, to expedite the soil excavation, the excavation contractor plans to work Monday-Saturday (~10 hour days) with only Sunday off.
– Additional IM (soil) Offsite Backfill Soil Sampling is performed. – Surface Water Pollution Prevention Plan Inspections & Maintenance is ongoing.
Week of April 08, 2018
– Soil Excavation, Hauling, and Disposal on the North Side of the WJC Site continues.
– Confirmation Soil Sampling on the North Side of the WJC Site is initiated.
– Surface Water Pollution Prevention Plan Inspections & Maintenance is ongoing.
Week of April 15, 2018
– Soil Excavation, Hauling, Disposal, on the North Side of the WJC Site continues.
– Confirmation Soil Sampling on the North Side of the WJC Site continues.
– Backfilling soil on the North Side of the WJC Site is initiated.
– Surface Water Pollution Prevention Plan Inspections & Maintenance is ongoing.
Week of April 22, 2018
– Confirmation Soil Sampling on the North Side of the WJC Site is completed.
– Backfilling Soil on the North Side of the WJC Site is completed.
– Surface Water Pollution Prevention Plan Inspections & Maintenance is ongoing.
Week of April 29, 2018
– Equipment Mobilization, Minor Demolition, Concrete Cutting and Soil Excavation, Hauling, and Disposal on the South Side of the WJC Site.
– Surface Water Pollution Prevention Plan Inspections & Maintenance is ongoing.
We hope you find this update helpful. We will continue to provide necessary updates to the schedule as the remediation work progresses. Please feel free to contact me at (804) 788-4485 or sarahhuddle@thinkalbright.com if I may be of further assistance. Wilson Jones Company is committed to working with the VDEQ and the community to complete the project and bring the property back to productive use.
Best regards,
Sarah Huddle,
APR Public Information Coordinator,
Former Acme Visible Records site—Crozet, VA
Attachment: Interim Measures (IM) (soil) Project Schedule – Update 02 – Click here for PDF
cc: Ryan Kelly, Corrective Action Project Manager, VDEQ-Office of Remediation Programs
[Received from Ms. Huddle, as PDF document link, and converted to text.]